Anglia Decor
Prepared for Gareth · ref EA9AFB

Epoxy resin floor for the 1,200 m² warehouse

Total£82,603.20inc VAT

Gareth, thank you for walking us round the Ipswich warehouse. Below is the epoxy floor we talked through for the 1,200 m² racking and loading area, priced line by line with the rate per m² or per metre on each line. We work over three weekends, one zone at a time, so the warehouse keeps trading. Tick either extra if you would like it and the total updates as you go.

What is included

Everything in the price, grouped so it is easy to follow. Tick the polyurethane topcoat or the coving if you would like them, and the total updates.

Preparation
Preparation sub-total£10,015
Floor system
Floor system sub-total£47,325
Line marking and safety
Line marking and safety sub-total£5,116
Programme and site
Programme and site sub-total£6,380
Subtotal (ex VAT)£68,836.00
VAT at 20%£13,767.20
Total£82,603.20
VAT no. GB123456700

Not included: moving stock, racking or machinery out of each zone (we can price this if you need it); heating to hold the building at 15°C or above during the works and the cure (below that, epoxy hardly cures); repairs to the slab beyond the crack and joint repairs listed. If the moisture test shows a damp slab, we agree a moisture-tolerant primer and its price with you before we start. Payments: 20% to book the weekends, 40% when zone 1 is handed back, and the balance within 30 days of the final handover.

This price is good until Sunday 1 November.

When we can do it

7 to 22 November

We have pencilled in three weekends, one zone at a time, so the rest of the warehouse keeps running: zone 1 on 7 and 8 November, zone 2 on 14 and 15 November and zone 3 on 21 and 22 November. Each weekend runs the same way: grinding, repairs and the primer on the Saturday, then the self-levelling coat once the primer has cured, with the walkways, bay lines and hatched zones laid into the finish. Each coat needs 12 to 24 hours at 15 to 20°C before the next one goes on, so the last coat in a zone goes down late on the Sunday. People can walk on it 24 hours after that and forklifts can go back on after 72 hours, so expect each zone back in full use from the Thursday. Full chemical cure takes 5 to 7 days at 15 to 20°C. If you tick the polyurethane topcoat, it adds one more coat to each zone on the Monday, while the zone is still closed, so each zone is back in full use from the Friday instead. The building needs to be held at 15°C or above through the works and the cure; below that, epoxy hardly cures.

Floors we have laid

Epoxy and resin floors from our recent jobs: warehouses, factories, workshops and car parks.

What our clients say

5.0 on Google. These are from our Google reviews, word for word.

★★★★★Andrew Taylor-Cary

AD Ltd carried out a very professional job. Their team repaired 150m2 factory flooring, to an exceptional finish. Definitely will use again.

★★★★★mondo matt

A highly professional and well-organized company. They managed both my clients and the policyholders with efficiency and care. All CDM and health & safety requirements were meticulously handled, ensuring seamless operations within a busy, functioning industrial unit. Exceptional service all around.

★★★★★Henry Groenendyk

Having received quotations from a number of commercial decorating companies for the painting of the exterior of our Warehouse, Anglia Decor Ltd were very competitive and offered the best overall specification for the job together with a guarantee for the work. Once a commencement date had been agreed they turned up on time and did an efficient job in preparing the surfaces before commencing the painting. I would certainly use this company again.

★★★★★Peter Wiffen

Great service, we were kept up to date from start to finish, workers were very efficient and the finish product was great, would highly recommend them.

★★★★★Jon Mulchrone

Very professional workforce

★★★★★THC (Ray)

Good company, reasonable price, top notch jobs, very friendly operatives and money worth of product delivery. Very nice finishing. I highly recommend this company to anyone.

About Anglia Decor

Anglia Decor Ltd., established in 2010 and based in Great Dunmow, Essex, carries out industrial refurbishment services across the UK. We have grown from a specialist painting contractor into a full-service provider covering industrial painting, resin flooring, commercial roofing and cladding, delivering complete building envelope solutions from a single, reliable team. We work with facilities managers, property owners, main contractors and local authorities on projects of every size, from a factory repaint or warehouse floor coating to full-scale roof replacements and multi-trade refurbishments. Every project runs to one standard, with a named project manager, well-trained operatives and detailed RAMS for every job. Anglia Decor has installed epoxy floors in manufacturing plants, distribution warehouses, pharmaceutical packaging areas, data centres, retail stockrooms, MOT workshops, and commercial showrooms.

Why Anglia Decor

If there is a better option for your project, we will tell you, even if it means we don't quote. No jargon, no hidden costs, no surprises. Anglia Decor invests 30 to 50% of total project time in preparation because it is the single factor that determines whether the floor lasts 5 years or 20. We stand behind our work with honest, no-quibble warranties on every project, typically 10 to 25 years on coatings and cladding systems, with 10-year insurance-backed guarantees available for extra peace of mind.

  • CHAS accredited
  • £10m public and employers liability insurance
  • A named project manager and weekly progress updates
  • Diamond grinding or shot blasting to FeRFA standards
  • Markings applied into the epoxy finish, not painted on top
  • Phased installations and weekend work available
  • Manufacturer guarantees included
  • No-quibble warranties on every project

Floor layout and terms

Tap a document to open it.

  • 74 KB
  • Terms, please read before accepting

Talk it through with us

Steve Massey, Anglia Decor

If anything is unclear, or you would like to change the system, the colour or the weekends, call or email Steve and we will talk it through.

Total inc VAT
£82,603.20